Contents
Abbreviations
Executive Summary
1.1 Background
1.2 Scope of the EM&A Report
1.3 Organization Structure
1.4 Summary of Construction Works
1.5 Summary of EM&A Programme Requirements
1.6 Status of Statutory Environmental Compliance with the Environmental Permit
1.7 Status of Other Statutory Environmental Requirements
2 EM&A Results for Tung Chung East
2.1 Air Quality
2.2 Noise Monitoring
2.3 Water Quality Monitoring
2.4 Soft Shore Ecological Monitoring
2.5 EM&A Site Inspection
2.6 Waste Management Status
2.7 Implementation Status of Environmental Mitigation Measures
2.8 Summary of Exceedances of the Environmental Quality Performance Limit
2.9 Summary of Complaints, Notification of Summons and Successful Prosecutions
3.1 Construction Programme for the Coming Month
3.2 Key Issues for the Coming Month
3.3 Monitoring Schedule for the Coming Month
4 Conclusion and Recommendation
Annexes
Annex A Project Organisation
Annex B Environmental Mitigation Implementation Schedule
Annex C Status of Statutory Environmental Requirements
Annex D Air
Quality
Annex D1 Calibration Certificates
Annex D2 Monitoring Schedule
Annex D3 Monitoring Results
Annex D4 Event and Action Plan
Annex E Noise
Annex E1 Calibration Certificates
Annex E2 Monitoring Schedule
Annex E3 Monitoring Results
Annex E4 Event and Action Plan
Annex F Water
Quality
Annex F1 Calibration Certificates
Annex F2 Monitoring Schedule
Annex F3 Monitoring Results
Annex F4 Event and Action Plan
Annex G Soft
Shore Ecology
Annex G1 Monitoring Schedule
Annex G2 Monitoring Results
Annex G3 Event and Action Plan
Annex I Monitoring Schedule for the Next Reporting Period
C&D |
Construction and Demolition |
CAP |
Contamination Assessment Plan |
CEDD |
Civil Engineering and Development Department |
CWD |
Chinese White Dolphin |
DCM |
Deep Cement Mixing |
DO |
Dissolved Oxygen |
EIA |
Environmental Impact Assessment |
EIAO |
Environmental Impact Assessment Ordinance |
EIS |
Ecologically Important Stream |
EM&A |
Environmental Monitoring and Audit |
EP |
Environmental Permit |
EPD |
Environmental Protection Department |
ER |
Engineer's Representative |
ERM |
ERM-Hong Kong, Limited |
ET |
Environmental Team |
HVS |
High Volume Sampler |
IEC |
Independent Environmental Checker |
PDA |
Planned Development Area |
RAP |
Remediation Action Plan |
RR |
Remediation Report |
SS |
Suspended Solid |
TCB |
Tung Chung Bay |
TCE |
Tung Chung East |
TCNTE |
Tung Chung New Town Extension |
TCW |
Tung Chung West |
The Project |
Tung Chung New Town Extension (East) |
THW |
Tai Ho Wan |
TSP |
Total Suspended Particulate |
Updated EM&A Manual |
Updated Environmental Monitoring and Audit Manual for Tung Chung New Town Extension prepared by ERM under Agreement No. CE 60/2017 (EP) and deposited to EPD under Environmental Permit No. EP-519/2016 |
Tung Chung New Town Extension (TCNTE) is one of the major initiatives under the Government's multi-pronged approach to increase land supply to meet Hong Kong's medium- to long-term needs for housing, economic and social developments. The Environmental Impact Assessment (EIA) Report for TCNTE (Register No. AEIAR-196/2016) was approved on 8 April 2016 and the Environmental Permit (EP) No. EP-519/2016, covering the construction and operation of TCNTE, was granted on 9 August 2016. The EIA Report and EP cover both Tung Chung East (TCE) and Tung Chung West (TCW). ERM-Hong Kong, Limited (ERM) is commissioned to undertake the role of Environmental Team (ET) for the construction and operation of TCE Project (¡§the Project¡¨) in accordance with the requirements specified in the EP, Updated Environmental Monitoring and Audit (EM&A) Manual, EIA Report of the TCNTE project and other relevant statutory requirements. The construction of the Project commenced on 9 July 2018.
This is the Monthly EM&A report presenting the EM&A works carried out during the period from 1 to 30 September 2018 for the Project in accordance with the Updated EM&A Manual. As informed by the Contractor, major activities in the reporting period are summarised in Table 1 below, together with the key issues and the key mitigation measures:
Table 1 Major Activities in the Reporting Period
Activities |
Key Issues |
Key Mitigation Measures |
Land-based Works |
|
|
¡P Demolition of site office near Century Link and Man Tung Road ¡P Removal of rock armour above +2.5mPD ¡P Preparation works for diversion of existing box culvert |
¡P Dust emission ¡P Waste management for C&D Materials ¡P Noise from barge and plant operation during normal working hours and restricted hours |
¡P Good site practices ¡P Regular water spraying on stockpiles ¡P Sorting and reuse of C&D materials as far as practicable |
|
|
|
Marine-based Works |
|
|
¡P Installation of pipe piles and sheet piles for ground investigation and wave protection measures ¡P Removal of rock armour below +2.5mPD ¡P Marine ground investigation works ¡P Laying of geotextile and sand blanket for reclamation works and Deep Cement Mixing (DCM) trial embankment ¡P Marine filling works ¡P Diversion of existing box culvert |
¡P Elevation in SS due to sediment loss from sand blanket laying and marine filling works ¡P Disturbance to Chinese White Dolphin |
¡P Provision of perimeter silt curtain for the Project ¡P Implementation of Dolphin Watching for the marine-based works ¡P Provision of a leading seawall of at least 200m before marine filling works |
A summary of monitoring and audit activities conducted in the reporting period is listed below:
Air Quality Monitoring 6 sessions
Noise Monitoring 6 sessions
Water Quality Monitoring 13 sessions
Soft Shore Ecological Monitoring 1 session
Environmental Site Inspection 4 sessions
Environmental Management Meeting 1 session
Environmental auditing works, including weekly site inspections of construction works conducted by the ET, audit of works vessels and audit of implementation of Dolphin Watching Plan were conducted in the reporting period. Based on the audit results and the observation for the reporting period, environmental pollution control and mitigation measures for the Project were properly implemented.
Snapshots of EM&A Activities in the Reporting Period
|
|
Soft Shore Ecological Monitoring conducted by ET |
Inspection of Silt Curtain after Adverse Weather |
|
|
Water Quality Monitoring conducted by ET |
Noise Monitoring conducted by ET |
Breaches of Action and Limit Levels for Air Quality
No exceedance of Action and Limit Levels was recorded for construction air quality monitoring in the reporting period.
Breaches of Action and Limit Levels for Noise
No exceedance of Limit Levels was recorded for construction noise monitoring in the reporting period. However, Action Level was triggered from one (1) environmental complaint related to noise nuisance received on 11 September 2018 during the reporting period. Investigation was conducted for this noise nuisance in accordance with the Event and Action Plan and the complaint handling process as stated in the Complaint Management Plan. Based on the noise monitoring events conducted in the reporting period, there was no exceedance of limit levels. Nevertheless, the Contractor was reminded to reduce construction noise levels, as far as practicable, especially when working next to the residential areas around the Project.
Breaches of Action and Limit Levels for Water Quality
The water quality monitoring results obtained during the reporting period generally complied with the corresponding Action and Limit Levels stipulated in the Baseline Monitoring Report. Relevant investigation and follow-up actions were conducted according to the EM&A programme when the water quality in terms of Dissolved Oxygen (DO), Turbidity and Suspended Solids (SS) exceeded the corresponding Action and Limit Levels. The preliminary investigation findings suggested that the exceedances were not related to the Project.
Soft Shore Ecological Monitoring
The impact monitoring conducted during the reporting period showed that there was no evidence showing significant change in intertidal communities when compared against the data obtained during baseline monitoring. The ET will continue to observe the change in density or the distribution pattern of horseshoe crab, seagrass and intertidal soft shore communities taking into account natural fluctuation in the occurrence and distribution pattern such as due to seasonal change.
Environmental Complaints, Non-compliance & Summons
There was no notification of summons or prosecution recorded in the reporting period.
Three (3) environmental complaints were received in the reporting period. Investigations were conducted for each of the environmental complaints in accordance with the complaint handling process as stated in the Complaint Management Plan. Environmental complaints in the reporting period are summarized in Table 2.
Table 2 Summary of Environmental Complaints
|
Complaint(s) |
Investigation/Follow up action(s) |
1 |
One environmental complaint related to noise nuisances at works area near Ying Tung Estate on 11 September 2018. |
Based on the information provided by the ER and the Contractor, supplemented the regular/ad-hoc noise monitoring conducted around the Project area, there was no exceedance of noise limit levels and non-compliance was not observed. Nevertheless, the Contractor was reminded to reduce construction noise levels, as far as practicable, especially when working next to the residential areas around the Project. No construction works in the evenings / restricted hours would be allowed without a valid Construction Noise Permit. The ET will continue to check the implementation status of the mitigation measures and conduct noise monitoring as per EM&A requirements.
|
2 |
Two environmental complaints related to waste management for the demolition of site offices near Century Link and Man Tung Road were received on 12 and 26 September 2018. |
Based on the information provided by the ER and the Contractor, supplemented the regular/ad-hoc site inspections conducted around the Project area, it was observed that the Contractor had fulfilled the requirements as stated in the Waste Management Plan to maintain temporary stockpiles and implemented trip-ticket system to ensure Construction and Demolition (C&D) materials were disposed properly. The Contractor also followed the waste management hierarchy as stated in the Waste Management Plan in handling the waste generated from the site clearance work for the site offices. Relevant waste materials from the site offices were reused, recovered and recycled where applicable. Nevertheless, the Contractor was reminded to implement all relevant mitigation measures of waste management implications and follow the requirements as stated in the approved Waste Management Plan. The ET will continue to check the construction works and the implementation status of the mitigation measures. |
Reporting Change
There was no reporting change in the reporting period.
Upcoming Works for the Next Reporting Period
Works to be undertaken in the next monitoring period of October 2018 are summarized in Table 3 below, together with the key issues and the key mitigation measures:
Table 3 Major Activities for the Next Reporting Period
Activities |
Key Issues |
Key Mitigation Measures |
Land-based Works |
|
|
¡P Erection of chain link fence at Area 58 ¡P Removal of rock armour above +2.5mPD ¡P Preparation works for diversion of existing box culvert |
¡P Dust emission ¡P Waste management for C&D Materials ¡P Noise from barge and plant operation during normal working hours and restricted hours |
¡P Good site practices ¡P Regular water spraying on stockpiles ¡P Sorting and reuse of C&D materials as far as practicable |
|
|
|
Marine-based Works |
|
|
¡P Installation of pipe piles and sheet piles for ground investigation and wave protection measures ¡P Removal of rock armour below +2.5mPD ¡P Installation of silt curtain near Tai Ho Wan ¡P Laying of geotextile and sand blanket and ground improvement works for reclamation works and Deep Cement Mixing (DCM) trial embankment ¡P Marine filling works ¡P Diversion of existing box culvert ¡P Marine ground investigation works |
¡P Elevation in SS due to sediment loss from sand blanket laying and marine filling works ¡P Disturbance to Chinese White Dolphin |
¡P Provision of perimeter silt curtain for the Project ¡P Implementation of Dolphin Watching for the marine-based works ¡P Provision of a leading seawall of at least 200m before marine filling works |
The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures. The ET will also recommend to the Contractor about the environmental toolbox topics on the abovementioned key issues for the next reporting period.
Tung Chung New Town Extension (TCNTE) is one of the major initiatives under the Government's multi-pronged approach to increase land supply to meet Hong Kong's medium- to long-term needs for housing, economic and social developments. The Environmental Impact Assessment (EIA) Report for TCNTE (Register No. AEIAR-196/2016) was approved on 8 April 2016 and the Environmental Permit (EP) No. EP-519/2016, covering the construction and operation of TCNTE, was granted on 9 August 2016. The EIA Report and EP cover both Tung Chung East (TCE) and Tung Chung West (TCW).
ERM-Hong Kong, Limited (ERM) is commissioned to undertake the role of Environmental Team (ET) for the construction and operation of TCE Project (¡§the Project¡¨) in accordance with the requirements specified in the EP, Updated Environmental Monitoring and Audit (EM&A) Manual ([1]), EIA Report of the TCNTE project ([2]) and other relevant statutory requirements.
The TCE Project (¡§the Project¡¨) comprises the following elements:
1. Reclamation of the seabed by a non-dredged method at TCE to form a total of about 130 hectares of land;
2. Construction of about 4.9 kilometres of seawalls, with an eco-shoreline, three drainage box culvert outfalls, three circulation drains and a seawater intake at TCE;
3. Construction of a 470-metre (m) long multi-cell drainage box culvert at TCE;
4. Provision of infrastructure for Tung Chung Area 58, including construction of a single two-lane road with a footpath of about 270 m in length and the associated utility works;
5. Construction of roads, footbridges, drainage, sewerage, waterworks, sewage and salt water pumping stations, fresh water and salt water service reservoirs, and flood protection measures;
6. Provision of new cycle tracks connecting to the existing cycle track network;
7. Landscaping, reprovisioning and ancillary works; and
8. Implementation of environmental mitigation measures and environmental monitoring and audit works.
The location of the Project, including the associated infrastructure works, is shown in Figure 1.1. The construction and the reclamation related marine works of the Project commenced on 9 and 13 July 2018, respectively.
This is the Monthly EM&A Report for the Project which summarises the key findings of the EM&A programme during the reporting period from 1 to 30 September 2018 for the construction works.
The organization structure of the Project is shown in Annex A. The key personnel contact names and contact details are summarized in Table 1.1 below.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Civil Engineering and Development Department
|
Senior Engineer |
Eddie Lam |
2231 4445 |
Engineer
|
Colin Wong |
2231 4417 |
|
Engineer¡¦s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
9325 0903 |
Senior Resident Engineer |
Robo Lo |
6622 1130 |
|
Resident Engineer |
Vincent Leung |
9800 0448 |
|
Senior Inspector of Works
|
C K Liu |
9433 6255 |
|
Environmental Team (ET) (ERM-Hong Kong, Limited)
|
ET Leader |
Jovy Tam |
2271 3113 |
Deputy ET Leader |
Raymond Chow |
2271 3114 |
|
Independent Environmental Checker (IEC) (Black & Veatch Hong Kong Limited)
|
IEC |
Manuel Chua |
2608 7314 |
Deputy IEC
|
Ivan Ting |
9222 9490 |
|
Contractor (Contract No. NL/2017/03 TCNTE ¡V Reclamation and Advance Works) (Build King ¡V SCT Joint Venture)
|
Site Agent |
Keith Tse |
9383 6173 |
Construction Team Leader |
Lee Wai Man |
9481 6024 |
|
Environmental Officer |
Calvin Sze |
9205 9277 |
|
24-hour Complaint Hotline
|
- |
9862 2910 |
As informed by the Contractor, details of the major works carried out in this reporting period are listed below:
Land-based Works:
Demolition of site office near Century Link and Man Tung Road;
Removal of rock armour above +2.5mPD; and
Preparation works for diversion of existing box culvert.
Marine-based Works:
Installation of pipe piles and sheet piles for ground investigation and wave protection measures;
Removal of rock armour below +2.5mPD;
Marine ground investigation works;
Laying of geotextile and sand blanket for reclamation works and Deep Cement Mixing (DCM) trial embankment;
Marine filling works; and
Diversion of existing box culvert.
The environmental mitigation implementation schedule is presented in Annex B.
The status for all environmental aspects are presented in Table 1.2. The EM&A requirements remained unchanged during the reporting period.
Table 1.2 Summary of Status for the Environmental Aspects under the Updated EM&A Manual
Parameters |
Status |
Air Quality |
|
Baseline Monitoring |
The results of baseline air quality monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4
|
Impact Monitoring |
On-going for TCE, monitoring conducted three times every six days |
|
|
Noise |
|
Baseline Monitoring |
The results of baseline noise monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4
|
Impact Monitoring |
On-going for TCE, monitoring conducted once per week
|
Impact Monitoring for Road Traffic Noise during Operational Phase
|
To be conducted during operational phase |
Fixed Noise Commissioning Test |
To be implemented by the Contractor |
|
|
Water Quality |
|
Baseline Monitoring |
The results of baseline water quality monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4
|
Impact Monitoring |
On-going for TCE, monitoring conducted three times per week |
|
|
Waste Management |
|
Waste Monitoring |
On-going |
|
|
Land Contamination |
|
Contamination Assessment Plan (CAP), Remediation Action Plan (RAP) and Remediation Report (RR) |
Pending environmental site investigation and lab testing works for TCW |
|
|
Ecology |
|
Monitoring for Compensation Woodland
|
To be conducted when compensation woodland are planted |
Monitoring for Emergent Plant inside the future River Park
|
To be conducted in the future River Park |
Monitoring for Translocated Amphibians of Conservation Importance
|
To be conducted after translocation |
Monitoring for Preserved/Transplanted Plant Species of Conservation Importance
|
To be conducted after preservation/ transplantation |
Monitoring for Tung Chung Stream EIS and Wong Lung Hang EIS
|
To be conducted under TCW |
Eco-shoreline Monitoring |
To be conducted when eco-shoreline at TCE PDA and Road P1 is built
|
Tung Chung Bay and Tai Ho Wan Baseline Monitoring |
The results of baseline soft shore ecological monitoring at Tung Chung Bay and Tai Ho Wan were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4
|
Tung Chung Bay and Tai Ho Wan Impact Monitoring |
On-going for TCE, monitoring conducted quarterly |
|
|
Landscape and Visual |
|
Baseline Monitoring |
The results of baseline landscape and visual monitoring were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
|
Site Environmental Audit |
|
Regular Site Inspection
|
On-going |
Dolphin Watching Plan implementation measures
|
Under implementation by the Contractor |
Works Vessel Travel Route Plan implementation measures
|
Under implementation by the Contractor |
Silt Curtain Deployment Plan implementation measures |
Under implementation by the Contractor |
|
|
Spill Response Plan implementation measures |
Under implementation by the Contractor |
|
|
Waste Management Plan implementation measures |
Under implementation by the Contractor |
|
|
Complaint Hotline and Email Channel
|
Under implementation by the Contractor |
Environmental Log Book |
On-going |
Taking into account the construction works, impact monitoring of air quality, noise, water quality and waste management were carried out in the reporting period. The monitoring schedule of air quality, noise, water quality monitoring and soft shore ecological monitoring are provided in Annex D2, Annex E2, Annex F2 and Annex G1, respectively.
The EM&A programme also involved environmental site inspections and related auditing conducted by the ET for checking the implementation of the required environmental mitigation measures recommended in the approved EIA Report and relevant EP submissions, including Dolphin Watching Plan, Works Vessel Travel Route Plan, Silt Curtain Deployment Plan, Spill Response Plan and Waste Management Plan. To promote the environmental awareness and enhance the environmental performance of the contractors, environmental trainings and regular environmental management meetings were conducted during the reporting period, which are summarized as below:
One (1) environmental management meeting was held with the Contractor, ER, ET, IEC and CEDD on 26 September 2018; and
Environmental toolbox trainings on noise control measure, dust control measure and handling of chemicals provided by the Contractor for the workers on 5, 12 and 19 September 2018.
The status of statutory environmental compliance with the EP conditions under the EIAO, submission status under the EP and implementation status of mitigation measures are presented in Table 1.3.
Table 1.3 Status of Submissions and Implementation Status of Mitigation Measures under EP
EP Condition |
Submission / Implementation Status |
Status |
2.1 |
Set up of Community and Professional Liaison Groups |
Community and Professional Liaison Groups were set up. |
2.1 |
Complaint Management Plan |
Accepted by EPD |
2.5 |
Employment of Qualified Ecologist(s) |
Qualified Ecologists have been employed to carry out work relating to ecological aspects. |
2.6 |
Employment of Surveillance Team |
Surveillance Team has been employed to conduct regular site inspection. |
2.11 |
Management Organizations |
Accepted by EPD |
2.12 |
Construction Works Schedule and Location Plans |
Accepted by EPD |
2.13 |
Works Vessel Travel Route Plan |
Accepted by EPD |
2.14 |
Eco-shoreline Implementation Plan |
To be prepared no later than 3 months before the commencement of construction of the eco-shoreline at TCE |
2.15 |
Dolphin Watching Plan |
Accepted by EPD |
2.16 |
Silt Curtain Deployment Plan |
Accepted by EPD |
2.17 |
Spill Response Plan |
Accepted by EPD |
2.18 |
Plan on Provision of Buffer Zones |
To be prepared no later than 3 months before the commencement of construction works at Tung Chung Valley |
2.19 |
River Park Plan |
To be prepared no later than 3 months before the commencement of construction works at Tung Chung Valley |
2.20 |
Habitat Enhancement and Translocation Plan for Amphibian Species of Conservation Importance |
To be prepared no later than 3 months before the commencement of construction works at Tung Chung Valley |
2.21 |
Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance |
To be prepared no later than 3 months before the commencement of construction works at Tung Chung Valley |
2.22 |
Detailed Compensatory Woodland Planting Plan |
To be prepared no later than 3 months before the commencement of construction works at Tung Chung Valley |
2.23 |
Plan for Review of Use of New Low Noise Road Surfacing Material(s) |
To be prepared no later than 3 months before the commencement of roadworks |
2.24 |
Waste Management Plan |
Accepted by EPD |
2.25 |
(i) no dredging of marine sediment shall be carried out for the Project (ii) all reclamation filling works shall be carried out within a leading seawall of at least 200m; and (iii) silt curtains surrounding the reclamation area shall be deployed in accordance with the Silt Curtain Deployment Plan |
Under implementation Under implementation
Under implementation
|
2.26 |
Implement Silt Curtain Deployment Plan and Spill Response Plan |
Under implementation
|
2.27 |
Implement dolphin exclusion zone of 250m around the reclamation site at Tung Chung East during the installation of the perimeter silt curtains and any re-deployment of the perimeter silt curtains by Qualified Ecologist(s) |
Under implementation
|
2.28 |
Once the perimeter silt curtains are installed or re-deployed, the Dolphin Watching Plan shall be implemented as part of the EM&A programme |
Under implementation
|
2.29 |
(i) no underwater blasting and percussive piling shall be carried out for the Project; and (ii) air compressors and other noisy equipment mounted on works vessels shall be acoustically-decoupled |
Under implementation
Under implementation
|
2.30 |
Implement Works Vessel Travel Route Plan Implement Eco-shoreline Implementation Plan Implement Dolphin Watching Plan |
Under implementation To be implemented Under implementation |
2.31 |
Implement Plan on Provision of Buffer Zones, River Park Plan, Habitat Enhancement and Translocation Plan for Amphibian Species of Conservation Importance, Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance and Detailed Compensatory Woodland Planting Plan |
To be implemented |
2.32 |
Implement
Plan for review of the use of new road surfacing material(s) |
To be implemented Under implementation |
2.33 |
Install noise barriers and low noise road surfacing at the extended Chung Mun Road and Road D3 All noise mitigation measures implemented shall be properly maintained during the operation of the above roads |
To be implemented
|
2.34 |
Implement a deodouriser with an odour removal efficiency of at least 95% shall be installed, operated and maintained within each sewage pumping station. The exhaust of the deodouriser shall be oriented away from sensitive receivers; and all odourous facilities of each sewage pumping station shall be enclosed and negative pressure shall be maintained within the facilities. |
To be implemented
|
2.35 |
Enclose all the pumps inside a building structure |
To be implemented
|
2.36 |
(i) a 100% standby pumping capacity shall be installed and maintained (ii) a 50% spare pumping capacity shall be installed and maintained (iii) dual-feed power supply shall be installed and maintained; and (iv) an emergency facility with a 6-hour storage capacity of average dry weather flow shall be installed and maintained. |
To be implemented To be implemented To be implemented To be implemented
|
The environmental licenses and permits, including environmental permit, waste discharge license, registration as chemical waste producer and construction noise permit, which are valid in the reporting period are presented in Annex C. No non-compliance with environmental statutory requirements was recorded.
The EM&A programme for the Project required environmental monitoring for air quality, noise, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts. The EM&A requirements and related findings for each component are summarized in the following sections.
According to the Updated EM&A Manual ([3]) of the Project, impact air quality monitoring in terms of 1-hour Total Suspended Particulate (TSP) was conducted three (3) times every six (6) days when the highest dust impact was expected. The Action and Limit Levels of the air quality monitoring is provided in Table 2.1 below.
Table 2.1 Action and Limit Levels for 1-hour TSP
Location |
Action Level, µg/m3 |
Limit Level, µg/m3 |
Monitoring station for Tung Chung East |
279 |
500 |
Portable direct reading dust meters were used to measure 1-hour TSP levels in undertaking the air quality monitoring for the Project. The proposed use of portable direct reading dust meters was submitted to IEC and obtained agreement from the IEC as stated in Section 5.5 of the Updated EM&A Manual. With the use of direct reading dust meter, it can allow prompt and direct results for the EM&A reporting and the implementation of the event and action plan. The portable direct reading dust meter would be calibrated every year against High Volume Sampler (HVS) to check the validity and accuracy of the results measured by direct reading method.
The monitoring location and equipment used in the impact air quality monitoring programme are summarized in Table 2.2 and illustrated in Figure 2.1. Copies of the calibration certificates for the equipment are presented in Annex D1, which showed that the portable direct reading dust meter is capable of providing comparable results with that provided by a HVS.
Table 2.2 Air Quality Monitoring Details
Monitoring Station |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
DM-1 |
Tung Chung Area 56 ¡V Ying Tung Estate |
1-hour TSP |
Three times per six days during the construction period of the Project |
3, 7, 13, 19, 24 & 29 Sep 2018 |
1-hour TSP Dust Meter SIBATA LD-5R (S/N: 620402) |
Remark: It should be noted that impact monitoring at other construction dust monitoring locations at TCE as stated in the Updated EM&A Manual will commence after the flat intake (for Monitoring Stations DM-2, DM-3 and DM-4). |
The schedule for air quality monitoring during the reporting period is provided in Annex D2.
The monitoring results for 1-hour TSP are summarized in Table 2.3. The monitoring data and the graphical presentation are provided in Annex D3.
Table 2.3 Summary of 1-hour TSP Monitoring Results in the Reporting Period
Monitoring Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
DM-1 |
36 |
22-89 |
279 |
500 |
The major dust sources in the reporting period included excavation, craning, sand blanket laying and material handling works under the Project as well as nearby traffic emissions.
All the 1-hour TSP results were below the Action and Limit Levels at the monitoring location in the reporting period. No action is thus required to be undertaken in accordance with the Event and Action Plan presented in Annex D4.
According to the Updated EM&A Manual ([4]) of the Project, impact noise monitoring was conducted once per week during the construction phase of the Project. The Action and Limit Level for construction noise of the Project is provided in Table 2.4 below.
Table 2.4 Action and Limit Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
0700 - 1900 hours on normal weekdays |
When one documented complaint is received |
75 dB(A) * |
Notes:
Limit level is exceeded when Leq ≥ 75 dB(A). If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.
* Reduce to 70 dB (A) for schools and 65 dB (A) during school examination periods.
Noise monitoring was performed using sound level meter at the designated monitoring stations NMS-CA-1A ([5]) and NMS-CA-4 (Figure 2.2; Table 2.5) in accordance with the requirements stipulated in the Updated EM&A Manual. Acoustic calibrator was deployed to check the sound level meters at a known sound pressure level. Details of the deployed equipment are provided in Table 2.5. Copies of the calibration certificates for the equipment are presented in Annex E1.
Table 2.5 Noise Monitoring Details
Monitoring Station (1) |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
NMS-CA-1A (2) |
Residential premise in Tung Chung East ¡V Century Link
|
30-minute measurement between 0700 and 1900 on normal weekdays (Monday to Saturday). Leq, L10 and L90 would be recorded. |
Once per week for 30 mins during the construction period of the Project |
19, 24 and 29 September 2018 |
Sound Level Meter: Rion NL-52 (S/N: 00331805)
Acoustic Calibrator: LARSON DAVIS CAL200 (S/N: 11333) |
NMS-CA-4 |
Residential premise in the reclamation area next to Tung Chung East ¡V Ying Tung Estate
|
3, 7, 13, 19, 24 and 29 September 2018 |
|||
Remarks: (1) It should be noted that impact monitoring at other construction noise monitoring locations at TCE as stated in the Updated EM&A Manual will commence after the flat intake of residential premise in TCE (for Monitoring Station NMS-CA-1) and operation of schools (for Monitoring Stations NMS-CA-2 and NMS-CA-3). (2) Impact monitoring at monitoring station NMS-CA-1A commenced on 19 September 2018 in view of the close vicinity of the construction works near the residential area at Century Link.
|
The schedule for noise monitoring during the reporting period is provided in Annex E2.
Results for noise monitoring are summarized in Table 2.6. The monitoring data and the graphical presentation are provided in Annex E3.
Table 2.6 Summary of Construction Noise Monitoring Results in the Reporting Period
Monitoring Station |
Average , dB(A), Leq (30mins) |
Range, dB(A), Leq (30mins) |
Limit Level, dB(A), Leq (30mins) |
NMS-CA-1A |
71.2 |
68.9-72.1 |
75 |
NMS-CA-4 |
65.2 |
62.1-69.1 |
75 |
Major noise sources during the noise monitoring included noise from crane and breaker operation (for monitoring station NMS-CA-1A), welding, excavation works, armour rock removal, sheet piling and grab barge works, nearby traffic noise and aircraft noise and nearby concurrent project. It should be noted that the temporary crane and breaker operation was conducted near the monitoring station NMS-CA-1A during the monitoring events and the monitoring results were observed to be higher when compared to those recorded for the monitoring station NMS-CA-4. The ET will keep on checking whether noise mitigation measures are properly implemented for the works of the Project.
No noise Limit Level exceedance was recorded in the reporting period. However, Action Level was triggered from one (1) environmental complaint related to noise nuisance received on 11 September 2018 during the reporting period. Investigation was conducted for the complaint in accordance with the Event and Action Plan (Annex E4) and the details are provided in Section 2.9.
Impact water quality monitoring was carried out to ensure that any deterioration of water quality was detected, and that timely action was taken to rectify the situation. Impact water quality monitoring was undertaken three days per week since the commencement of marine works during the reporting period in accordance with the Updated EM&A Manual. Each impact water quality monitoring was scheduled such that the interval between two impact water quality monitoring was more than 36 hours to record representative water quality data throughout the week during the marine works.
Two (2) replicate in-situ measurements and samples were collected at each monitored water depth of each designated monitoring stations. Dissolved Oxygen (DO), pH value, salinity, temperature and turbidity were measured in-situ whereas the level of suspended solids (SS) were determined by ALS Technichem (HK) Pty Ltd which is a HOKLAS accredited laboratory.
The Action and Limit Levels of the water quality monitoring are provided in Table 2.7.
Table 2.7 Action and Limit Levels for Water Quality
Parameters |
Action Level |
Limit Level |
DO in mg/L (Surface, Middle & Bottom) |
Surface and Middle 5.9 mg/L [1]
Bottom 5.6 mg/L |
Surface and Middle 4 mg/L [1]
Bottom 2 mg/L
|
SS in mg/L (Depth-averaged) |
13.5 mg/L
|
23.5 mg/L |
Turbidity in NTU (Depth-averaged) |
17.1 NTU |
23.5 NTU |
Notes:
(1) For DO, non-compliance occurs when monitoring results is lower than the limits.
(2) For SS and Turbidity, non-compliance occurs when monitoring results is larger than the limits
The locations of the monitoring stations under the Project are shown in Figure 2.3 and Table 2.8.
Table 2.8 Locations of Impact Water Quality Monitoring Stations and the Corresponding Monitoring Requirements
Monitoring Station |
Description |
Coordinates |
Parameters (1) |
Frequency |
Depth |
|
|
|
Easting |
Northing |
|
|
|
TCE-WQM1 |
Near Airport Channel |
811838 |
817341 |
Dissolved Oxygen (DO) (mg/L and % saturation) Temperature (¢XC) Turbidity (NTU) Salinity (ppt) pH Water depth (m) Suspended Solid (SS) (mg/L) |
Impact monitoring: 3 days per week, at mid-flood and mid-ebb tides during the construction period of the Project
|
3 water depths: 1m below sea surface, mid-depth and 1m above seabed. If the water depth is less than 3m, mid-depth sampling only. If water depth less than 6m, mid-depth may be omitted |
TCE-WQM2a |
Marine Park 1 |
814439 |
819879 |
|||
TCE-WQM2b |
Marine Park 2 |
814439 |
821905 |
|||
TCE-WQM3A |
Outlet of Tai Ho Wan |
814705 |
817859 |
|||
TCE-WQM4 |
HKBCF |
813344 |
818849 |
|||
TCE-C1 |
Control Station - Outside Airport Channel |
804247 |
815620 |
|||
TCE-C2 |
Control Station - Sunny Bay |
819460 |
821473 |
|||
Notes: |
Table 2.9 summarizes the equipment used in the impact water quality monitoring works. Copies of the calibration certificates are attached in Annex F1.
Table 2.9 Water Quality Monitoring Equipment
Equipment |
Model |
Water Sampler |
Kahlsico Water Samplers |
Multi-parameter Water Quality System (measurement of DO, Temperature, Turbidity, Salinity and pH) (Note 1) |
YSI ProDSS (S/N: 16H104233; S/N: 16H104234; S/N: 17E100747; S/N: 17H105557) YSI 6920 v2 (S/N: 0001C6A7; S/N: 00019CB2) |
Note 1: Two of the multi-parameter water quality systems were used at each monitoring station during each survey day. |
The schedule for water quality monitoring during the reporting period is provided in Annex F2.
A total of 13 monitoring events for impact water quality monitoring were conducted at all designated monitoring stations during the reporting period. The monitoring event during mid-ebb tide on 15 September 2018 was cancelled due to the issue of Strong Wind Signal No.3 of Typhoon Mangkhut. Impact water quality monitoring results and graphical presentations are provided in Annex F3.
Action level and limit level exceedances were recorded for water quality impact monitoring in the reporting period and the event and action plan (Annex F4) was undertaken. Investigations on the action and limit level exceedances were conducted and summarized in Table 2.10 below.
Table 2.10 Details of Exceedances Recorded for Water Quality Monitoring
Group |
Date |
Tide |
Parameter |
Station |
Type |
Remarks |
1 |
01 Sep 2018 |
ME |
DO (S&M) |
All stations |
Action |
The exceedances were not considered as caused by the construction of the Project due to the following reasons: Areas of reclamation related marine works undertaken under the Project were surrounded by silt curtain, which was inspected daily by the Contractor and endorsed by ER and observed to be in good condition and functioning well, except minor defect was found for silt curtain on 18, 20 and 22 September 2018 after the approach of typhoon Mangkhut. The defect was fixed on 23 September 2018 and inspected by the Contractor and endorsed by ER. DO levels at the monitoring stations were higher than or similar to those at corresponding control/upstream stations. No marine works were undertaken on 15 and 25 September 2018. During summer season, the marine water experienced temperature and salinity stratification, where layers of water build up with different levels of temperature and salinity which prevent mixing of water masses, leading to hypoxia (low oxygen levels) at the sea bottom. |
|
|
ME |
DO (B) |
TCE-WQM1 |
Action |
|
|
|
ME |
DO (B) |
TCE-WQM2a |
Action |
|
|
|
ME |
DO (B) |
TCE-WQM2b |
Action |
|
|
|
ME |
DO (B) |
TCE-WQM3A |
Action |
|
|
|
MF |
DO |
All stations |
Action |
|
|
04 Sep 2018 |
ME |
DO |
All stations |
Action |
|
|
|
MF |
DO |
All stations |
Action |
|
|
06 Sep 2018 |
ME |
DO |
All stations |
Action |
|
|
|
MF |
DO (S&M) |
TCE-WQM2b |
Action |
|
|
|
MF |
DO (S&M) |
TCE-WQM4 |
Action |
|
|
|
MF |
DO (B) |
TCE-WQM1 |
Action |
|
|
|
MF |
DO (B) |
TCE-WQM2a |
Action |
|
|
|
MF |
DO (B) |
TCE-WQM2b |
Action |
|
|
08 Sep 2018 |
ME |
DO |
TCE-WQM1 |
Action |
|
|
|
ME |
DO |
TCE-WQM2a |
Action |
|
|
|
ME |
DO |
TCE-WQM2b |
Action |
|
|
|
ME |
DO (B) |
TCE-WQM3A |
Action |
|
|
|
MF |
DO (B) |
TCE-WQM1 |
Action |
|
|
|
MF |
DO |
TCE-WQM2a |
Action |
|
|
|
MF |
DO |
TCE-WQM2b |
Action |
|
|
|
MF |
DO (B) |
TCE-WQM3A |
Action |
|
|
|
MF |
DO (S&M) |
TCE-WQM4 |
Action |
|
|
11 Sep 2018 |
ME |
DO |
All stations |
Action |
|
|
|
MF |
DO (S&M) |
TCE-WQM1 |
Action |
|
|
|
MF |
DO (S&M) |
TCE-WQM2a |
Action |
|
|
|
MF |
DO (S&M) |
TCE-WQM2b |
Limit |
|
|
|
MF |
DO (S&M) |
TCE-WQM3A |
Action |
|
|
|
MF |
DO (S&M) |
TCE-WQM4 |
Action |
|
|
|
MF |
DO (B) |
All stations |
Action |
|
|
13 Sep 2018 |
ME |
DO |
All stations |
Action |
|
|
|
MF |
DO |
All stations |
Action |
|
|
15 Sep 2018 |
MF |
DO |
All stations |
Action |
|
|
18 Sep 2018 |
ME |
DO (S&M) |
TCE-WQM3A |
Action |
|
|
20 Sep 2018 |
ME |
DO |
TCE-WQM1 |
Action |
|
|
|
ME |
DO (B) |
TCE-WQM2a |
Action |
|
|
|
ME |
DO (B) |
TCE-WQM2b |
Action |
|
|
|
MF |
DO (B) |
TCE-WQM2b |
Action |
|
|
22 Sep 2018 |
ME |
DO (B) |
TCE-WQM1 |
Action |
|
|
|
ME |
DO (B) |
TCE-WQM2a |
Action |
|
|
|
ME |
DO (B) |
TCE-WQM3A |
Action |
|
|
|
MF |
DO |
TCE-WQM2b |
Action |
|
|
|
MF |
DO (B) |
TCE-WQM1 |
Action |
|
|
|
MF |
DO (B) |
TCE-WQM2a |
Action |
|
|
25 Sep 2018 |
ME |
DO (B) |
TCE-WQM1 |
Action |
|
|
|
ME |
DO |
TCE-WQM2b |
Action |
|
|
|
ME |
DO |
TCE-WQM3A |
Action |
|
|
|
MF |
DO (B) |
TCE-WQM1 |
Action |
|
|
|
MF |
DO (B) |
TCE-WQM2a |
Action |
|
|
|
MF |
DO |
TCE-WQM2b |
Action |
|
|
|
MF |
DO |
TCE-WQM3A |
Action |
|
|
27 Sep 2018 |
ME |
DO |
All stations |
Action |
|
|
|
MF |
DO |
All stations |
Action |
|
|
29 Sep 2018 |
ME |
DO (S&M) |
TCE-WQM1 |
Action |
|
|
|
ME |
DO |
TCE-WQM2a |
Action |
|
|
|
ME |
DO |
TCE-WQM2b |
Action |
|
|
|
ME |
DO |
TCE-WQM4 |
Action |
|
|
|
MF |
DO |
TCE-WQM1 |
Action |
|
|
|
MF |
DO |
TCE-WQM2a |
Action |
|
|
|
MF |
DO |
TCE-WQM2b |
Action |
|
|
|
MF |
DO (S&M) |
TCE-WQM3A |
Action |
|
|
|
MF |
DO |
TCE-WQM4 |
Action |
|
|
|
|
|
|
|
|
2 |
01 Sep 2018 |
ME |
SS |
TCE-WQM1 |
Action |
The exceedances were not considered as caused by the construction of the Project due to the following reasons: Areas of reclamation related marine works undertaken under the Project were surrounded by silt curtain, which was inspected daily by the Contractor and endorsed by ER and observed to be in good condition and functioning well. Monitoring stations are located nearby the shore. In view of the rainy weather, surface runoff from the nearby land mass to the sea might be resulted, thus increasing the levels of Suspended Solids of the water. |
|
|
ME |
SS |
TCE-WQM3A |
Action |
|
|
|
|
|
|
|
|
3 |
08 Sep 2018 |
ME |
SS |
TCE-WQM2b |
Action |
The exceedances were not considered as caused by the construction of the Project due to the following reasons: Areas of reclamation related marine works undertaken under the Project were surrounded by silt curtain, which was inspected daily by the Contractor and endorsed by ER and observed to be in good condition and functioning well. The monitoring stations are located further away from the Project works area when compared with monitoring stations TCE-WQM3A and TCE-WQM4 where exceedances were not recorded.
|
|
|
MF |
SS |
TCE-WQM2b |
Action |
|
|
11 Sep 2018 |
ME |
SS |
TCE-WQM1 |
Action |
|
|
|
MF |
SS |
TCE-WQM2b |
Action |
|
|
13 Sep 2018 |
ME |
SS |
TCE-WQM2a |
Action |
|
|
|
MF |
SS |
TCE-WQM2a |
Action |
|
|
|
MF |
SS |
TCE-WQM2b |
Limit |
|
|
29 Sep 2018 |
ME |
SS |
TCE-WQM1 |
Action |
|
|
|
MF |
SS |
TCE-WQM2a |
Action |
|
|
|
|
|
|
|
|
4 |
27 Sep 2018 |
MF |
SS |
TCE-WQM3A |
Action |
The exceedances were not considered as caused by the construction of the Project due to the following reasons: Areas of reclamation related marine works undertaken under the Project were surrounded by silt curtain, which was inspected daily by the Contractor and endorsed by ER and observed to be in good condition and functioning well. Site observations confirmed no silt plumes or observable issues during marine works on 27 September 2018, including installation of pipe pile and sheet pile, sand filling and geotextile laying. |
|
|
MF |
Turbidity |
TCE-WQM3A |
Action |
|
ME: Mid-ebb; MF: Mid-flood DO(B): Bottom-depth DO; DO (S&M): Surface and middle-depth averaged DO All Stations: TCE-WQM1, TCE-WQM2a, TCE-WQM2b, TCE-WQM3A and TCE-WQM4 |
Based on the preliminary investigation conducted for each of the monitoring day with potential action and limit level exceedances with the Contractor, the ER and the IEC, there is no evidence showing the exceedances were related to the Project. Nevertheless, the Contractor was reminded to implement all relevant mitigation measures for the marine works, including regular checking of silt curtain integrity and maintain good site practice. The ET will keep on checking monitoring data, plant, equipment and Contractor¡¦s working methods. The ET will also conduct further investigation, including the review of water quality monitoring data from adjacent projects, to substantiate the exceedances were not considered as caused by the construction of the Project.
According to the Updated EM&A Manual ([6]) of the Project, impact soft shore ecological monitoring has to be conducted quarterly at each survey location at Tung Chung Bay (TCB) and Tai Ho Wan (THW) covering wet and dry seasons during the marine construction of the Project. The soft shore ecological monitoring consisted of qualitative walk-through surveys, quantitative transect surveys and sedimentation rate monitoring at the accessible survey locations of TCB and THW.
For qualitative walk-through surveys, the accessible shoreline of TCB and THW at each of the three shore heights: 2 m, 1.5 m and 1 m above Chart Datum was surveyed, and organisms encountered were recorded and their relative abundance noted. In particular, active search of horseshoe crabs and seagrasses were conducted to confirm whether these species are present along the sites.
For quantitative transect survey, one 50 ¡V 100 m horizontal (belt) transect (actual length subject to the site conditions) was surveyed at each of the three shore heights: 2 m, 1.5 m and 1 m above Chart Datum of each survey location. On each transect, five quadrats (50 cm x 50 cm) were placed randomly in each transect to assess the abundance and distribution of flora and fauna. For each quadrat, surface layer to 5 cm depth was sieved and microbenthic organisms (e.g. crustaceans) were recorded and identified. Density of organisms was expressed as individuals / m2. Areas with seagrass were also recorded and identified and other information, such as the percentage cover, were also recorded. Sessile animals such as barnacles and oysters in each quadrat were not counted but estimated as percentage cover on the rock surface. All species of algae (encrusting, foliose and filamentous) were also identified and recorded by estimating the percentage cover on the rock surface. All organisms were identified to the lowest possible taxonomic level (at least Genus level). Species encountered outside the quadrat but in the vicinity of survey transect were also recorded.
For sedimentation rate monitoring, to avoid disturbance to the mudflat and nuisance to navigation, no fixed marker/monitoring rod was installed at the monitoring stations. A high precision Global Navigation Satellite System (GNSS) real time location fixing system (or equivalent technology) was used to locate the station in the precision of 1 mm, which is reasonable under flat mudflat topography with uneven mudflat surface only at micro level.
Measurements were taken directly on the mudflat surface. The Real Time Kinematic GNSS (RTK GNSS) surveying technology was used to measure mudflat surface levels and 3D coordinates of a survey point. The RTK GNSS survey was calibrated against a reference station in the field before and after each survey. The reference station is a survey control point established by the Lands Department of the HKSAR Government or traditional land surveying methods using professional surveying instruments such as total station, level and/or geodetic global navigation satellite system. The coordinates system is in HK1980 GRID system. The reference control station was surveyed and established by traditional land surveying methods using professional surveying instruments such as total station, level and/or geodetic GNSS. The accuracy was down to mm level and higher than the proposed RTK GNSS cm level so that the reference control station has relatively higher accuracy. As the reference control station has higher accuracy, it was set as true evaluation relative to the RTK GNSS measurement. All position and height correction were adjusted and corrected to the reference control station.
The precision of the measured mudflat surface level reading (vertical precision setting) was within 10 mm (standard deviation) after averaging the valid survey records of the XYZ HK1980 GRID coordinates. Each survey record at each station was computed by averaging at least three measurements that are within the above specified precision setting. Both digital data logging and written records were collected in the field. Field data on station fixing and mudflat surface measurement were recorded.
The schedule for soft shore ecological monitoring during the reporting period is provided in Annex G1.
Impact soft shore ecological monitoring was conducted at three (3) monitoring locations at Tung Chung Bay (TCB), situated in the eastern side (TCB1), southern side (TCB2) and western side (TCB3) as well as one (1) monitoring location at Tai Ho Wan (THW) as shown in Figure 2.4 during the reporting period. Representative photographs taken during the impact monitoring are presented in Figure 2.5.
For qualitative walk-through surveys, horseshoe crabs and intertidal soft shore communities were recorded while seagrass beds were not observed during the impact monitoring. The survey results for each monitoring location are summarized in Table 2.11 below and detailed in Annex G2.
Table 2.11 Summary of Qualitative Walk-through Surveys
Date and Time |
Location |
Horseshoe Crabs |
Seagrass |
No. of Other Intertidal Species |
||
No. of Species |
No. of Individuals |
No. of Species |
Area Coverage (m2) |
|||
5/9/2018 08:30-12:30
|
TCB2 |
1 |
3 |
0 |
0 |
40 |
7/9/2018 11:00-14:30
|
THW |
2 |
6 |
0 |
0 |
43 |
10/9/2018 13:30-17:00
|
TCB3 |
2 |
19 |
0 |
0 |
44 |
11/9/2018 14:00-17:30 |
TCB1 |
2 |
10 |
0 |
0 |
45 |
For quantitative transect surveys, a total of 4,071 individuals were recorded from all transects at monitoring stations TCB1-3 and THW. The most abundant group of intertidal soft shore communities recorded was gastropods, with a total of 3,842 individuals (relative abundance of 94.4% and density of 256 individual m-2). The summary of the top three dominant species at each shore height of each monitoring station and the complete list of species and density recorded are presented in Annex G2. When compared with the results obtained during the baseline monitoring as presented in the Baseline Monitoring Report ([7]), higher number of intertidal species were recorded at each monitoring location, though the abundance / density of intertidal communities was observed to be lowered. Nevertheless, there is no indication of change in composition of intertidal communities during the reporting period.
The mudflat surface levels at the four selected monitoring stations in September 2018 and the corresponding XYZ HK1980 GRID coordinates are presented in Table 2.12. When compared with the results obtained during the baseline monitoring as presented in the Baseline Monitoring Report ([8]), the sediment levels at each monitoring station generally increased. The ET will continue to observe the trend of change in sediment levels over time for further comparison and review.
Table 2.12 Results of Sedimentation Rate Monitoring
Monitoring Station |
Northing (m) |
Easting (m) |
Z level at Sep 2018 (mPD) |
Remarks |
TCB1 |
816068.626 |
811129.309 |
1.545 |
Soft mudflat |
TCB2 |
815812.382 |
810917.245 |
1.322 |
Soft mudflat |
TCB3 |
816027.632 |
810696.839 |
1.314 |
Soft mudflat |
THW |
817472.067 |
815850.407 |
1.380 |
Soft mudflat |
The impact monitoring results showed that there was no evidence showing significant change in intertidal communities when compared against the data obtained during baseline monitoring. No action is thus required to be undertaken in accordance with the Event and Action Plan presented in Annex G3. The ET will continue to observe the change in density or the distribution pattern of horseshoe crab, seagrass and intertidal soft shore communities taking into account natural fluctuation in the occurrence and distribution pattern such as due to seasonal change.
Site inspections were carried out on a weekly basis with the Contractor and ER to monitor the implementation of proper environmental pollution control and mitigation measures for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts under the Project. In the reporting period, four (4) site inspections were carried out on 6, 13, 20 and 26 September 2018.
Key observations during the site inspections are summarized in Table 2.13.
Table 2.13 Key Observations Identified during the Site Inspection in this Reporting Month
Inspection Date |
Environmental Observations |
Recommendations/ Remarks |
6 September 2018
|
Ground Investigation (GI) platform (Dong Ah 107) Stagnant water in drip tray GI platform (Dong Ah 105) Stagnant water in drip tray Chemicals without drip tray GI platform (Kong Yeung 88) Stagnant water in lower deck |
GI platform (Dong Ah 107) The contractor was reminded to clear stagnant water. GI platform (Dong Ah 105) The contractor was reminded to clear stagnant water; and The contractor was reminded to place chemicals in drip tray. GI platform (Kong Yeung 88) The contractor was reminded to clear stagnant water.
|
13 September 2018
|
Works Area near Man Tung Road Accumulated debris at site Pak Mong Pier Used chemicals at site |
Works Area near Man Tung Road The contractor was reminded to dispose of the accumulated debris. Pak Mong Pier The contractor was reminded to regularly remove used chemicals.
|
20 September 2018
|
Works Area near Ying Tung Estate A water-filled barrier was found to trap stagnant water Chemicals without drip tray Accumulated debris at site Suspended chemical leakage Stagnant water in drip tray Diesel drum without chemical labels Works Area near Century Link No noise barrier provided when working near residential areas |
Works Area near Ying Tung Estate The contractor was reminded to seal the opening of the barrier to avoid stagnant water; The contractor was reminded to place chemicals in drip tray; The contractor was reminded to remove accumulated debris; The contractor was reminded to cover the ground by canvas and drill on the canvas to avoid soil contamination by chemicals; The contractor was reminded to clear stagnant water in drip tray; The contractor was reminded to provide labelling for chemicals. Works Area near Century Link The contractor was reminded to provide noise barrier when working near residential areas to reduce noise nuisance from construction works. |
26 September 2018
|
Vessel (Tat Fat 11) Diesel drum without chemical labels Stagnant water in tyres |
Vessel (Tat Fat 11) The contractor was reminded to provide labelling for chemicals. The contractor was reminded to clear stagnant water in the tyres.
|
The Contractor has rectified all of the observations identified during environmental site inspections in the reporting period.
The Contractor has registered as chemical waste producer under the Contract. Sufficient numbers of receptacles were available for general refuse collection and sorting.
All dump trucks engaged on site was equipped with GPS during the reporting period. The Surveillance Team of the ET conducted regular site inspection on the dump trucks and their track records. Illegal dumping and landfilling of C&D materials were not recorded during the reporting period.
As informed by the Contractor, wastes generated during this reporting period include mainly imported fill, non-inert construction wastes and recyclable materials. Reference has been made to the waste flow table prepared by the Contractor. The quantities of different types of wastes are summarised in Table 2.14. It should be noted that the Contractor voluntarily engaged in tree clearance works after the approach of the Typhoon Mangkhut in mid-September 2018 and hence more non-inert construction wastes were generated in the reporting period.
Table 2.14 Quantities of Different Waste Generated
Month/ Year |
Inert C&D Materials (a) (m3) |
Imported Fill (m3) |
Inert Construction Waste Re-used (m3) |
Non-inert Construction Waste (b) (m3) |
Recyclable Materials (c) (kg) |
Chemical Wastes (kg) |
|
9 to 31 Jul 18 |
0 |
6,665 (d) |
0 |
20.7
|
0 |
0 |
|
1 to 31 Aug 18 |
0 |
20,036 |
0 |
110.1
|
96,740 |
0 |
|
1 to 30 Sep 18 |
0 |
14,086 |
0 |
356.3 |
11,120 |
0 |
|
Notes: (a) Inert construction wastes include hard rock and large broken concrete, and materials disposed as public fill. (b) Non-inert construction wastes include general refuse disposed at landfill. (c) Recyclable materials include metals, paper, cardboard, plastics and others. (d) Updated figure is presented. |
A summary of the Environmental Mitigation Implementation Schedule is presented in Annex B. The necessary mitigation measures were implemented properly for the Project.
Results for air quality monitoring (1-hour TSP) complied with the Action/ Limit levels in the reporting period. One (1) Action level exceedance for construction noise was recorded from one (1) environmental complaint related to noise nuisance. No Project-related Action/ Limit level exceedances were recorded for water quality after preliminary investigation. Results for the soft shore ecological monitoring did not indicate any change in composition of intertidal communities when compared to the baseline monitoring results.
Cumulative statistics on exceedances is provided in Annex H.
There was no notification of summons or prosecution recorded in the reporting period.
One (1) environmental complaint related to noise nuisances at works area near Ying Tung Estate on 11 September 2018 and two (2) environmental complaints related to waste management for the demolition of site offices near Century Link and Man Tung Road on 12 and 26 September 2018 were received during the reporting period. Investigations were conducted for each of the environmental complaints in accordance with the complaint handling process as stated in the Complaint Management Plan.
Based on the information provided by the ER and the Contractor, supplemented the regular/ad-hoc noise monitoring conducted around the Project area, there was no exceedance of noise limit levels and non-compliance was not observed. Nevertheless, the Contractor was reminded to reduce construction noise levels, as far as practicable, especially when working next to the residential areas around the Project. No construction works in the evenings / restricted hours would be allowed without a valid Construction Noise Permit. The ET will continue to check the implementation status of the mitigation measures and conduct noise monitoring as per EM&A requirements.
Based on the information provided by the ER and the Contractor, supplemented the regular/ad-hoc site inspections conducted around the Project area, it was observed that the Contractor had fulfilled the requirements as stated in the Waste Management Plan to maintain temporary stockpiles and implemented trip-ticket system to ensure Construction and Demolition (C&D) materials were disposed properly. The Contractor also followed the waste management hierarchy as stated in the Waste Management Plan in handling the waste generated from the site clearance work for the site offices. Relevant waste materials from the site offices were reused, recovered and recycled where applicable. Nevertheless, the Contractor was reminded to implement all relevant mitigation measures of waste management implications and follow the requirements as stated in the approved Waste Management Plan. The ET will continue to check the construction works and the implementation status of the mitigation measures.
Statistics on complaints, notifications of summons, successful prosecutions are summarised in Annex H.
As informed by the Contractor, the major works for the Project in October 2018 will be:
Land-based Works:
Erection of chain link fence at Area 58;
Removal of rock armour above +2.5mPD; and
Preparation works for diversion of existing box culvert.
Marine-based Works:
Installation of pipe piles and sheet piles for ground investigation and wave protection measures;
Removal of rock armour below +2.5mPD;
Installation of silt curtain near Tai Ho Wan;
Laying of geotextile and sand blanket and ground improvement works for reclamation works and Deep Cement Mixing (DCM) trial embankment;
Marine filling works;
Diversion of existing box culvert; and
Marine ground investigation works.
Potential environmental impacts arising from the above upcoming construction activities in the next reporting period of October 2018 are mainly associated with noise from barge and plant operation during normal working hours and restricted hours, elevation in SS due to sediment loss from sand blanket laying and marine filling works, disturbance to Chinese White Dolphin (CWD) during marine works, and waste management for C&D materials. The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures. The ET will also recommend to the Contractor about the environmental toolbox topics on the abovementioned key issues for the coming month.
The tentative schedules for environmental monitoring in October 2018 are provided in Annex I.
This EM&A Report presents the findings of the EM&A activities undertaken during the period from 1 to 30 September 2018 in accordance with the Updated EM&A Manual and the requirements of the Environmental Permit (EP-519/2016).
Air quality (1-hour TSP), noise, water quality (DO, turbidity and SS) and soft shore ecological monitoring were carried out in the reporting period.
Results for 1-hour TSP complied with the Action and Limit levels in the reporting period. One (1) Action level exceedance for construction noise was recorded from one (1) environmental complaint related to noise nuisance in the reporting period. No Project-related Action/ Limit level exceedances were recorded for water quality after preliminary investigation. Results for the soft shore ecological monitoring did not indicate any change in composition of intertidal communities when compared to the baseline monitoring results.
Environmental site inspections were carried out during the reporting period. Recommendations on remedial actions were given to the Contractor for the deficiencies identified during the site inspections.
There was no notification of summons or prosecution recorded in the reporting period. One (1) environmental complaint related to noise nuisances at works area near Ying Tung Estate and two (2) environmental complaints related to waste management for the demolition of site offices near Century Link and Man Tung Road were received on 11, 12 and 26 September 2018 during the reporting period. Investigations were conducted for each of the environmental complaints in accordance with the complaint handling process as stated in the Complaint Management Plan.
The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.
([1]) ERM (2018a). Updated Environmental Monitoring and Audit Manual for Tung Chung New Town Extension. Deposited to EPD under EP-519/2016
([5]) Impact monitoring at monitoring station NMS-CA-1A commenced on 19 September 2018 in view of the close vicinity of the construction works near the residential area at Century Link.